Calabogie Dam Rock Anchor Project
In 2019, Ontario Power Generation initiated rehabilitation work at the Calabogie Generating Station to extend the operational lifespan of the existing dam infrastructure. After decades of continuous service, structural reinforcement measures were required to improve long-term stability and maintain the integrity of the dam structure. The project required specialized rock anchor installations through the concrete piers and into the underlying bedrock while working in close proximity to environmentally sensitive waterways and wildlife habitats.
Marathon Underground was selected to complete the rock anchor stabilization work using specialized drilling, coring, grouting, and post-tensioning techniques designed specifically for heavy civil and hydroelectric infrastructure applications.
The installation process began with coring a 32-inch diameter hole approximately 48 inches deep into the concrete structure to create a pinning cap. This enlarged section was designed to distribute structural loads across the existing concrete once the rock anchor system was tensioned. Marathon Underground then cored an 8-inch diameter hole approximately 25 feet through the concrete dam structure and an additional 20 feet into competent bedrock below.
Once drilling operations were completed, a crane was used to lower the pre-assembled rock anchor into position within the borehole. The anchor system was then grouted in place while leaving sufficient space near the surface for the anchor head and base plate assembly. Following installation, the anchor was post-tensioned to approximately 264 tonnes of force, equivalent to the weight of nearly eight fully loaded dump trucks. This tensioning process provided the required structural reinforcement by securely tying the multiple concrete layers of the dam into the underlying bedrock foundation.
Environmental protection was a critical component of the project due to the proximity of construction activities to the river system. Marathon Underground implemented comprehensive containment measures to prevent fluids or contaminants from entering the waterway. Equipment was operated within containment tubs, and compressed air drilling systems were utilized to direct drill cuttings into controlled collection systems for safe disposal.
An additional feature of the anchor design allowed the rock anchors to be re-tensioned in the future if required, providing long-term flexibility for ongoing dam maintenance and structural monitoring.
The Calabogie Dam Rock Anchor Project was successfully completed on schedule, on budget, and without significant safety or environmental incidents, demonstrating Marathon Underground’s expertise in complex dam rehabilitation, structural stabilization, and environmentally sensitive infrastructure construction.
Ontario Power Generation
Calabogie, ON
2019
- Rock anchors for dam stabilization
- Grouting
- Vertical drilling and coring
- Post-tensioning
Dam Rehabilitation and Structural Stabilization
Rock anchor installation through dam piers into competent bedrock
Concrete dam structure over bedrock adjacent to active waterway